Monday, April 29, 2024

I-81 Viaduct Project Contracts Department of Transportation

nysdot design build

The joint venture firm identified at least 20 community-based stakeholder organizations to engage as part of the pre-construction design-build process, with a particular focus on Spanish-language outreach. Our projects range from residential remodels, new custom homes, site planning, sustainable design and construction, landscape environments, hillside expansions and repair, in-house custom woodworking and concrete, boutique retail spaces, and industrial contemporary office renovations. Further contracts under the community grid plan would cover reconstruction of parts of I-690, which meets I-81 in downtown Syracuse, demolition of the viaduct, construction of Business Loop 81 and various bridge replacements, street reconstructions and other local street improvements. State transportation officials had planned for work on some of those contracts to start this year. With Board approval of this contract, SFTC will as part of Phase 1 review existing design work, conduct constructability review, value engineering, bottoms-up cost estimate and schedule.

nysdot design build

NY Moves Ahead on Syracuse I-81 Viaduct Replacement Project

The State is considering legislation to allow Design-Build project delivery for a limited number of transportation projects. This initiative is being considered to achieve time and cost savings as well as to expand the potential for use of innovative construction technology in some transportation projects. The Federal Government and several States use this project delivery method to assure the long term durability and quality of transportation projects, and New York State needs to have the capability to employ this method.

I-81 Contract 1 Open House Renderings

FHWA Approves $1B Expressway Cap Project to Reunite Buffalo, NY, Neighborhoods - Engineering News-Record

FHWA Approves $1B Expressway Cap Project to Reunite Buffalo, NY, Neighborhoods.

Posted: Thu, 22 Feb 2024 08:00:00 GMT [source]

Aaron and Britton both hold a Masters degree in Architecture from Southern California Institute of Architecture and understand firsthand the importance in executing thoughtful design and construction. The third planned contract’s scope would include improvements to streets in Syracuse’s Northside neighborhood, including rehabilitation of Bear Street between I-690 and the planned Business Loop 81. Dynamic Real Estate Partners is a client-driven real estate development firm. The company builds key relationships one project at a time to create successful and profitable outcomes while enhancing and benefiting the communities where it develops.

I-81 Viaduct Project - Phase 1, Contract 2

We are uniquely able to analyze the cost of construction during early design phases, guiding the design process in a more focused way. As part of HNTB's design work, the project design includes streetscape and landscape restoration and improvements. The streetscape pays close attention to context sensitive design and included the local community in the process through public involvement meetings while adhering the PROWAG, NYCDOT, NYC Parks and NYCDEP requirements. From single tenant retail to custom designed and built commercial and residential projects, Dynamic specializes in the design development and construction of real estate at every stage of the process. Our expertise in evaluating concepts and implementing ideas allows for skillful execution from initial design steps through timely completion. It includes street trees planted in a cobble-edged continuous trench with structural soil for greater vigor and longevity of the plantings.

nysdot design build

Focused on Development, Design & Building

Additionally, beginning on or about Monday, April 15, at 9 a.m., the following ramps at the northern interchange of I-81/I-481 in the Town of Cicero, Onondaga County, will be closed to traffic. GLYNNdesignbuild is a custom architecture and general contracting company in Los Angeles, California offering both design-build and traditional general contracting services and full architectural service. Although our specialty is design-build, we often build for other Owners as acting General Contractor working with an Architect. Neri’s order states that demolition of the viaduct could not begin until the supplement is completed, though he did allow work on the early contracts to proceed. Attorneys for Renew 81 then sought to reargue their points in order to prevent any work from moving forward, but in May the judge denied the request.

Comment Period Extended for the Draft Design Report/ Environmental Assessment for the NYS Route 33 Kensington ... - Buffalo Rising

Comment Period Extended for the Draft Design Report/ Environmental Assessment for the NYS Route 33 Kensington ....

Posted: Thu, 02 Nov 2023 07:00:00 GMT [source]

“The Interstate 81 Viaduct Project will serve as a national example of how thoughtful infrastructure can bring people together, promote growth, and increase prosperity for all communities,” New York Gov. Kathy Hochul (D) said at the groundbreaking. Salt City Constructors, LLC is comprised of three separate contractors consisting of Lancaster Development and Tully Construction Co., LLC dba L&T Construction, D.A. Collins Construction Co., Inc. and Cold Spring Construction Co., Inc.

During Phase I, SFTC will complete design validation, identify and negotiate early works packages, such as advanced utility relocations and final design, and develop the scope of work and price for Phase 2. Phase 1 will end if Metro and SFTC agree to a guaranteed maximum price and Metro will issue a supplement to the project contract to proceed to Phase 2, kicking off the construction portion of the project. As defined, the Design-Build method offers the client a single point of responsibility, thereby reducing Client risk and overall cost. We are able to manage your project from conceptual design through construction as your primary contact. We have found that this way of working offers a smooth transition between design and construction, more attention to detail during construction, and a more effective line of communication for the entire team.

I-81 Northern Interchange looking North

Earlier this year, state officials awarded a $296.4-million contract to Salt City Constructors LLC, a team of Lancaster Development and Tully Construction Co. Inc., for the first phase of work including the northern interchange reconstruction. Work on both contracts is scheduled to complete in late 2025, according to state Dept. of Transportation records. In addition to its significant experience with PDB, as well as technical experience in similar transit projects, SFTC had the highest-rated plan for “cultural competency” in its contract proposal. SFTVC’s cultural competency plan best encompassed consideration of race, ethnicity, gender, immigration status, languages spoken, socioeconomics and public transportation dependency, among others.

I-81 Northern Interchange looking Northeast

As part of the project, HNTB landscape architects  designed small passive recreation public spaces along the roadway. These small parks include green infrastructure to collect and filter stormwater run-off, while providing the community with new gathering spaces with benches, special paving and lighting. They also collaborated with HNTB structural engineers to create safe and comfortable bicyclist/pedestrian access and provided landscape design and restoration on the Queens approach at First Calvary Cemetery. The scope of the first two contracts for the I-81 Viaduct Project includes reconstruction of interchanges at existing I-481 north and south of Syracuse.

Anthony Construction Corp. plus Rifenburg Construction Corp. and Crane-Hogan Structural Systems Inc. The new 6.7-mile light rail is planned to include 11 new light rail stations along Van Nuys Boulevard and will improve connections to and access between Van Nuys and Pacoima. Several Equity Focus Communities, which are census tracts that have a significant concentration of underserved populations, are close to the planned rail line.

The I-81 Viaduct Project Contract 1 will reconstruct the section of I-81 at the interchange of I-481 to BL 81 and convert I-481 to the new I-81 between Kirkville Road and the northern I-81/I-481 Interchange. NYSDOT continues to move forward with preparations for the start of the I-81 Viaduct project. Here you will find contract and phasing information as the project advances. While procedural in nature, this information is important to continue towards advancing this project to groundbreaking in 2022. “The project would result in traffic delays and backups (making the community grid into community gridlock),” attorneys for Renew 81 wrote in a court filing.

When working with other Architects as part of a team, we are able to quickly grasp the design intent and offer architectural detailing support if requested. We hold weekly or bi-weekly meetings with the Owner and Architect to outline the project schedule, upcoming details, review change orders, and discuss any questions the team may have. The design-build contract focuses on constructing the northern interchange of Business Loop 81 (BL 81) and Interstate 81 (I-81) and reconstructing the new section of I-81 (former I-481) between Kirkville Road and the New York State Thruway (I-90). However, only work on the first three of eight planned contracts may currently proceed. Earlier this year, Onondaga County Supreme Court Judge Gerard Neri ordered the state to produce a supplemental environmental impact statement addressing issues raised by community advocates who oppose the community grid design.

The rail line will also provide key linkages with Metro bus lines, including the G Line (Orange) in Van Nuys and municipally operated bus lines. "Having engaged Dynamic Builders to construct some twenty industrial buildings, I am pleased to report that each project was delivered per agreed-upon construction specifications, in a timely manner, and at or below the construction contract price." The New York State Department of Transportation is alerting motorists that Interstate 81 northbound will be closed to traffic between Exit 16A and the interchange with Interstate 481 northbound in the City of Syracuse, Onondaga County, for two consecutive weekends beginning at 7 p.m. HNTB served as lead designer for the new Kosciuszko Bridge Project, which carries traffic over Newtown Creek between Brooklyn and Queens, New York. A new cable-stayed bridge, which replaces the structurally deficient, 76-year-old existing span, is among the region’s first major cable-stayed bridges. As the New York State Department of Transportation’s largest-ever design-build project, it also sets the precedent for future design-builds statewide.

Metro is planning to employ Progressive Design-Build (PDB), an innovative and potentially cost-efficient construction methodology, to build the light rail line. PDB has become more common in public-sector projects in recent years and has proven to help decrease project change orders, delays and cost overruns. PDB can also help reduce scope and schedule creep by addressing the highest risk elements much earlier in the process, well before construction begins. We offer schematic design/early design study, site planning, construction documents, and permitting. Full construction services include cost analysis, feasibility study, schedule analysis, construction, construction management, and client representation. The newly awarded contract’s scope covers reconstruction of the current southern interchange of I-81 and I-481, reconstruction of another I-481 interchange with State Routes 5 and 92 and improvements along other stretches of the interstate highway loop.

In December, Metro held a groundbreaking for advanced utility work on the first segment of the project. Metro has also been working with the Federal Transit Administration on federal funding and last month received a $600 million grant through the state Transit and Intercity Rail Capital Program (TIRCP). Metro has also been holding community open houses to offer more information about upcoming construction activities and what to expect, small business support programs and introduction of project staff. Provisions within the contract will ensure SFTC implements a robust plan to interact cross-culturally with the many diverse communities along the project corridor. The company was founded in 2002 by Aaron and Britton Glynn as a way to better control the construction process, insure quality detail in construction, and deliver projects to clients in a more efficient way.

No comments: